Why Goldcorp’s Project Pipeline Could Drive Long-Term Growth
Goldcorp (GG) has one of the strongest project pipelines in the industry. At Penasquito, the Pyrite Leach Project (or PLP) is 62% complete and expected to start commissioning in 4Q18, which is three months ahead of schedule. This project is expected to add ~1 million ounces of gold and 44 million ounces of silver over the current life of the mine.